Works for Phase 1 at Blocks C and D of J Satine can only begin after the foundation strengthening and structural repairs are fully completed.
Works for Phase 1 at Blocks C and D of J Satine can only begin after the foundation strengthening and structural repairs are fully completed.

KUALA LUMPUR – [UPDATED]


📝 Proposal to Continue Works:

The consulting engineers proposed resuming construction for SOHO Block, Block A, and Block B.


🚫 Block C & D On Hold:

DBKL stated that work on Blocks C and D can only begin after foundation strengthening and structural repairs are fully completed.


📄 Independent Engineer’s Report:

The proposal was based on a progress report dated 24 February, prepared and endorsed by a certified independent professional engineer.


✅ Safety Confirmation:

The building’s safety and stability have been certified by the engineers involved in the structural design.


📊 Ongoing Monitoring:

DBKL requires the consulting engineers to submit:

  • Monthly Progress Reports

  • Repair Completion Reports(Both must be verified by an independent consultant.)


💥 Incident Report:

DBKL received complaints about an explosion at the site from residents of PPR Wangsa Sari.


🤝 Engagement Session Required:The developer is required to hold a session with:

  • J Satine buyers

  • Wangsa Maju MP's Office

  • Federal Territories Department

  • National Housing Department➤ Must be held within two weeks after the stop-work notice is withdrawn.


News Come from Sinar Harian - 21 April 2025 07:18pm

 
 
 